(This article is reproduced with the kind permission of Navy Lookout)
Here we look at the French Navy’s ambitious project to construct a 75,000-tonne nuclear-powered, conventional aircraft carrier for delivery in the late 2030s
Background
In 2018 the Marine Nationale launched four studies into replacing its existing aircraft carrier, the FS Charles de Gaulle (CDG). The French government subsequently confirmed they would build another nuclear-powered vessel, the Porte Avions de Nouvelle Génération (PA-Ng) in 2020. For English-speaking audiences, the project is sometimes referred to as the Future French Carrier (FFC).
While French public finances are in an even more dire state than those of Britain, the MN benefits from well-managed defence procurement and a long-term defence industrial strategy far superior to chaotic UK practice. The MN has navigated the usual tired arguments that aircraft carriers are obsolete, too expensive etc. and succeeded in getting political support and approval for this mammoth project. The budget for FFC design and construction is officially €6 billion although most accept that €8 billion or more is realistic.
The project is now in the second of two de-risking and feasibility phases running from 2021 up to the end of 2025. The preliminary design phase concluded in early 2023 and was followed by the programme definition phase, which will run until late 2025 ahead of the System Functional Review. The first iteration of the design was unveiled in 2020 but this was significantly altered by 2022. The single unified ‘witches hat’ mast above the island (A feature of the FTI frigates) has been replaced with a more conventional arrangement. The hull form and flight deck layout has also evolved substantially and it should be emphasised that the design continues to develop and the final ship may look considerably different to the imagery published so far.
The detailed design phase will begin in 2025 through to 2032 although some manufacturing will start well in advance of 2032. The commitment to the programme was demonstrated by the placing of contracts for long lead items in April 2024. This included elements of the nuclear propulsion system and preparatory infrastructure work at the Chantiers de l’Atlantique shipyard.
The main construction and assembly will take place between 2032-35 with initial sea trials on nuclear power in early 2036. If this timetable can be met, then the ship is scheduled to commission in 2038.

Design
The MN says the FFC will need to be able to deliver the full spectrum effects from tactical to strategic, have adaptability for new technologies and aircraft types over an expected service life of 40 years. The ship will be able to launch heavily armed aircraft capable of relatively long-range sorties as well as supporting uncrewed air vehicles from the outset.
The outline design is for a 75,000-tonne ship, 305m long and 79m maximum beam (some sources suggest up to 78,000-tonne displacement). The flight deck and sponsons will have a considerable overhang from the main hull which has a beam of 39m at the waterline. The displacement also trumps the British Queen Elizabeth class, although this is of course, purely coincidental.
The 17,000m2 flight deck and hangars will accommodate an air group of about 30 Rafale and NGF together with two Hawkeye and up to 6 medium helicopters. (The rotary wing ASW element of the French carriers is noticeably lighter than UK practice). FFC is also intended to be compatible with USN aircraft, including the F/A-18E/F Super Hornet, F-35C Lightning, and CMV-22 Osprey. Two deck-edge lifts forward of the island can each carry two Rafale jets at a time from the hangar that extends two decks high and about two-thirds of the length of the ship.
At a cost of $1.321 billion, General Atomics is supplying two 90-metre Electromagnetic Launch Systems (EMALS) and the Advanced Arrestor Gear (AAG) set developed for the Ford-class. GA has already done the heavy lifting in developing this system that is now mature and proven in service on the Ford. Compared to the steam catapults of the CDG, EMALS enables an increased sortie launch rate, has a lower maintenance requirement and the power delivery can be accurately calibrated to suit the weight of the aircraft from small drones to NGF and Hawkeye. The flight deck has positions for three catapults, two over the bow and one on the port waist. It is unclear at present if two or three EMALS will be fitted, although this will not be clarified until the end of 2025.

The ship will be powered by two K22 nuclear reactors based on the K15 of the CDG. She will be an all-electric ship with generators producing around 80MW for the propulsion motors and 30MW for EMALS, combat systems and hotel load. Maximum speed is officially 27 knots but likely to be slightly faster in reality. Unlike the US/UK naval reactors that use highly enriched uranium (HEU), the K22 has a low-enriched uranium (LEU) core and requires refuelling about once every decade.
FFC will be armed with an unspecified number of Sylver VLS cells for Aster missiles or its successor, similar to the CDG with silos in sponsons amidships, port starboard. Close-in defence is provided by 4 Thales RapidFire 40 mm gun mounts as well as 3 SIMBAD-RC launchers for short-range Mistral missiles. There is also the expectation and associated power generation capacity available to fit directed energy weapons in future.
It is hoped the ship can be run with a total crew of around 2,000 including the air wing and command staff. Keeping the sailor numbers to this size would represent quite an achievement, the 25% larger Ford-class still requires more than double this complement.
One of the more complex but less obvious challenges in aircraft carrier design is the arrangement of weapon magazines and elevators. To maximise sorties rates, the safe movement of weapons from storage to the aircraft has to be carefully planned. The electromagnetic induction weapon lifts of the Ford-class offer major advantages but proved difficult to commission. The Highly Mechanised Weapon Handling System (HMWHS) developed for the QEC carriers may also be of interest to the French as they seek to minimise crew size.

Air group
The FFC will initially operate at least 3 types of fixed-wing crewed aircraft. Assuming the ship enters service around 2038, the Rafale-M will still be in service. However, its successor derived from the Système de Combat Aérien du Futur (SCAF) program, the Next Generation Fighter (NGF) intended to be the mainstay of French combat aviation in the 2040s.
NGF is a development effort between France, Germany, and Spain and will be a stealthy 6th-generation strike fighter aircraft. The NGF will be much larger than the Rafale-M, with an 18m long fuselage and a 14m wingspan, twin engines, two large weapon bays, and a V-tail. Just as the move from the Harrier to F-35 helped increase the displacement of the QEC carriers, the jump from Rafale to NGF is a major factor driving up the size of the FFC.
NGF programme is an approximate parallel of the Global Combat Air Programme (GCAP), the joint UK, Japanese and Italian effort to develop a new strike-fighter. NGF and GCAP are also part of a wider ‘system of systems’ confusingly both named the Future Combat Air System (FCAS) which includes uncrewed loyal wingmen and data backbones. NGF and GCAP alone are colossally ambitious and expensive multi-national projects with huge political and technical hurdles to overcome. Not least is the fact that Europe has not produced a ‘5th generation’ aircraft and does not have US industry’s wealth of experience in developing stealth aircraft technologies. If GCAP will be challenging, then NGF looks even more ambitious as it will also have to be carrier-capable.
The Marine Nationale will continue to operate the E-2 Hawkeye Airborne Early Warning and Control aircraft. Three new E-2Ds have been ordered from Northrop Grumman which will be delivered in 2028 and will eventually operate from the FFC. A key requirement is the ability to launch aircraft armed with tactical nuclear weapons – the Force Aéronavale Nucléaire (FANu). For the CDG this comprises a strike package of up to 22 Rafale jets and an E-2C Hawkeye.

Construction
The FFC will be designed and constructed by MO Porte-Avions, a joint venture comprising Naval Group (65%) and Chantiers de l’Atlantique (35%). This consortium is responsible for overall program management under the government’s Direction Générale de l’Armement (DGA), with the Atomic Energy Commission (CEA) overseeing TechnicAtome producing the nuclear reactors.
The ship will be constructed at the Chantiers de l’Atlantique shipyard in Saint Nazaire. This yard is used to constructing very large vessels including cruise ships over 200,000 tonnes but an aircraft carrier will present a far greater level of complexity. On completion, the ship will be fitted with temporary diesel generators to provide power to the motors for the passage to Toulon, where the fuelling of the nuclear cores and commissioning of the reactor will take place.
Since the arrival of CDG, the MN has always recognised the limitations of a single ship and has aspired to procure a second vessel. The Porte-Avions 2 (PA2) project was initiated in 2003 using the QEC design as the basis for a CATOBAR carrier but the project was suspended in 2009 and cancelled in 2013. Essentially by selecting a ‘gold standard’ conventional-launch, nuclear-powered vessel, in the CDG France possesses a first-rank carrier but cannot afford another ship and is therefore hampered by part-time availability. Given that the FFC will be even more expensive, a second ship of this class is also unlikely.
Aircraft carrier construction is a complex business. The De Gaulle, the QEC carriers and the USS Gerald R Ford all suffered significant technical problems at the outset of their careers that delayed their entry into service. The ambition of the MN to acquire such a powerful ship is admirable but whether this can be delivered by 2038 as planned is questionable. The world could look very different by the 2040s but the FFC should give France (and NATO) a very powerful naval power projection platform intended to last into the 2080s.